As Canberra heads into warmer weather, builders and concreters should plan how fresh concrete will be protected from rapid moisture loss. Hot weather can shorten working times, while direct sunlight, dry winds and low humidity increase evaporation and the risk of early cracking.
These conditions can affect slabs, driveways and paths even when air temperatures are relatively mild. Curing needs to retain moisture so concrete can continue developing strength and durability.
Good warm weather concreting practices include:
Evaporation retarders, including aliphatic alcohol, do not replace curing. Concrete still requires an appropriate curing method once finishing is complete.
Agree the curing method and duration before the pour, based on the project specification, concrete mix and supplier’s recommendations. Keep a record of the curing measures used as part of your site quality checks.